Gostern Wire rope rigging /Chain rigging /Lifting rigging

NEWS

Featured products

Application: Ship, iron and steel industry, petroleum chemical industry, coal mine
Application: Can use on different pulley or hoist, lever hoist and electrical hoist.
Application: Ship, iron and steel industry, and other decorative function sucn as pet and lock the door. Also can use on hoist and pulley.
Can hold such as: the tube, pipe, oval pipe, rectangular pipe, H-beam, I-beam, container and other big constructure.
Stud Link and Studless Link Anchor Chain are widely used on Floating Equipment, Ships(Boats), Oil Rigs and Mooring Buoys.
The anchor chain is made up of many links, and the size of the chain is shown as diameter-MM

Classic lifting site! Hinkley Point C, the largest nuclear power station in the UK

The Hinkley Point C nuclear power station is the largest infrastructure project ever undertaken in the UK. When completed, it will provide about 7% of the UK’s green electricity supply and create about 25,000 jobs during the construction process.

Classic1Classic2Classic3Classic4

SGC-250 ring rail crane will be the main lifting equipment at Hinkley Point C for four years and is expected to perform more than 700 lifts, assisted by 52 tower cranes.

Classic5Classic6

Developed and designed by Sarens which is Belgian hoisting giant, the SGC-250 ring rail crane has a maximum lifting moment of 250,000 tons per meter, a maximum lifting capacity of 5,000 tons and a maximum lifting capacity of 2,000 tons within a 100-meter radius. SGC-250 is also affectionately known as Big Carl, after Carl Sarens, the leader of Sarens.

Classic7

It is reported that SGC-250 rail crane was manufactured in Belgium and tested before being dismantled for transportation; All the parts used to assemble the rail crane were transported by 280 lorries to Somerset, England later.

Classic8Classic9Classic10

SGC-250 rail crane was assembled in August 2019 using five auxiliary cranes (including two CC2800 crawler cranes, one 220t, one 130-t and one 100-t mobile crane) after 10 weeks, overcoming the adverse factors such as strong winds and the small space of the construction site. The first lifting was realized in mid-September.